For this Arizona property, LEK crews assumed an aggressive timeline and project schedule for installing all new washers and dryers in each individual unit. Support work for these installations included:
- Completed successful asbestos testing
- Installed new electrical and sub panels to accommodate increased electrical loads
- Re-piped existing PEX hot and cold water lines to accommodate new inflow/outflow demands
- Completed all framing and finishing
Project Details
Client
Acacia Capital Corp
Location
1666 S. Extension
Mesa, AZ
Scope
304 occupied residential apartment units
Timeline
6 months
Cost
$3.17 Million